Project Timeline

Perdaman - Creating a cleaner and greener future

Project Timeline
Public announcement of project October 2018
Commencing community consultation February 2019
Permitting and environment approvals December 2019- December 2020
Engineering December 2020
Construction contract arrangements finalised October 2020
Financial close 2nd Quarter 2021
Field construction start 3rd Quarter 2021
Mechanical completion 4th Quarter 2024
Startup begins 1st Quarter 2025
Full production 2nd Quarter 2025