Project Timeline

Perdaman - Creating a cleaner and greener future

Project Timeline
Public announcement of project October 2018
Commencing community consultation February 2019
Permitting and environment approvals December 2019 – March 2020
Engineering October 2018
Construction contract arrangements finalised June 2019
Financial close 2nd quarter 2020
Field construction start 2nd quarter 2020
Mechanical completion 4th quarter 2023
Startup begins 1st quarter 2024
Full production 2nd quarter 2024