Project Timeline

Perdaman - Creating a cleaner and greener future

Project Timeline
Public announcement of project October 2018
Commencing community consultation February 2019
Permitting and environment approvals December 2019- June 2021
Engineering December 2020
Construction contract arrangements finalised October 2020
EPC Arrangement finalised March 2021
Financial close 4th Quarter 2021
Field construction start 1st Quarter 2022
Mechanical completion 1st Quarter 2024
Startup begins 2nd Quarter 2024
Full production 2nd Quarter 2025